Good airtightness is not simply about choosing the right products. It is about creating one continuous, durable airtight layer around the building and making sure every connection is properly sealed. This practical guide explains the key principles, installation methods and quality checks.
1. Airtightness Basics
Understanding the Building Envelope
A typical insulated building element has three main functions: external protection against weather and wind, thermal insulation, and an internal airtightness and/or vapour control layer.
Airtightness prevents uncontrolled air movement through the building envelope. Vapour control regulates moisture movement by diffusion. These are different functions, although one material may perform both.
The airtight layer must form an uninterrupted boundary around the heated or conditioned building volume. It follows the thermal building envelope, not the individual floors.
For example, a conventional two-storey house does not normally require an additional airtightness membrane between the ground floor and first floor when both storeys are within the same conditioned space.
Different Materials, One Continuous Layer
Depending on the construction, airtightness may be provided by internal plaster, membranes or suitably tested building boards. However, materials should never be assumed to be airtight without suitable product information or verification. Even airtight boards require correctly sealed joints, edges and penetrations.
The most important requirement is continuity at every junction: walls, roofs, floors, windows, doors and service penetrations.
Follow the thermal building envelope — and keep the airtight layer continuous.
2. Membrane Installation
Where Are Airtightness Membranes Needed?
In conventional masonry construction, a continuous internal plaster finish often provides the airtight layer of the walls. Airtightness membranes are therefore commonly used in insulated roof and ceiling constructions rather than across the masonry walls.
In timber frame buildings, airtightness membranes may also be installed on the walls. Alternatively, appropriately specified airtight boards can perform this function.
Regardless of the construction method, all airtight layers must be connected using suitable airtightness tapes or sealants.
Installing and Fixing the Membrane
Install membranes neatly, avoiding excessive folds, wrinkles and unnecessary tension. Allow for normal movement of the construction and follow the membrane manufacturer's installation instructions.
Membranes are commonly fixed to timber rafters, joists or studs using staples. Approximately 150 mm fixing centres along each supporting timber member are a useful practical guideline, subject to the membrane manufacturer's requirements.
Adequate mechanical fixing is important because the airtight layer may experience changing air-pressure loads during construction and throughout the building's life.
Staples and Accidental Damage
Where plasterboard is installed directly against the membrane, the lining can provide additional mechanical restraint, particularly at the supporting timbers. Properly installed staple penetrations may not require individual taping where the membrane system permits this arrangement.
However, visible tears, enlarged staple holes or other damage must always be repaired with suitable airtightness tape.
Practical tip: Keep a marker pen nearby during installation. Mark any accidental damage immediately so it can be easily identified and repaired during the sealing stage.
Where a separate service cavity is installed, assess how the membrane is supported and whether staple penetrations require additional sealing. Do not assume that every fixing is adequately protected.
Complete One Room at a Time
Whenever practical, install the membranes in one room and complete the sealing work before moving to the next.
Seal membrane overlaps, service penetrations, wall connections and marked repairs promptly after installation.
This is particularly important during colder weather. Depending on temperature and humidity, condensation may form on exposed membrane surfaces. Airtightness tapes cannot be expected to bond reliably to wet or condensation-covered materials.
Always check that membrane surfaces are clean and dry before applying adhesive tapes.
3. Airtightness Tapes & Sealants
Choosing the Right Airtightness Tape
Airtightness tapes such as (f)air tightness GREEN, BLACK, GREY and SPLIT PLUS are designed for applications including membrane overlaps, repairs, service penetrations and suitable connections to adjacent building components.
They can also be used for appropriate membrane connections around windows and roof windows, particularly in timber frame construction. However, membrane tapes should not automatically be substituted for dedicated window sealing tapes.
Always check whether a tape is intended for internal use only or is also suitable for external applications.
UV Exposure
UV resistance is important, even for tapes installed indoors. During construction, tapes may remain exposed to sunlight through windows or roof glazing for extended periods.
Excessive UV exposure can affect the tape backing or adhesive, and deterioration may not always be immediately visible. Observe the permitted exposure period and protect installed tapes as required.
Connecting Membranes to Masonry and Concrete
For membrane connections to suitable masonry, concrete or ICF surfaces, we generally recommend an appropriate airtightness sealant such as (f)air tightness OR.
The reason is straightforward: the adhesive layer on an airtightness tape is relatively thin and cannot easily compensate for uneven, porous or rough surfaces.
A sealant bead provides more material between the membrane and the substrate, helping accommodate surface irregularities.
Apply a continuous bead of minimum 8 mm diameter of (f)air tightness OR Airtight Sealant. Carefully press the membrane into the fresh sealant without completely flattening the bead, ensuring that sufficient sealant remains between the membrane and the substrate to accommodate surface irregularities.
This can be particularly useful on rough concrete blockwork. Nevertheless, the substrate must still be sound, sufficiently clean and suitable for adhesion. The underlying wall must also form part of a continuous airtight construction.
4. Window & Door Connections
Internal and External Window Sealing
Window and door connections require different functions on the inside and outside of the building.
Inside: The connection provides continuity with the building's airtight layer and normally has greater resistance to water vapour diffusion. (f)air tightness WISA IN has an approximate sd-value of 30 m.
Outside: The connection protects the joint against wind and weather, including driving rain where specified, while allowing greater potential for outward drying. WISA OUT and WISA OUT PLUS have approximate sd-values of 2 m.
The usual principle is "inside tighter than outside" in terms of vapour diffusion resistance. An external tape can still be windtight and airtight while remaining more vapour permeable. Product suitability and the moisture performance of the complete construction must always be considered.
Airtight Window Connections in Cavity Walls
In conventional cavity wall construction, the internal plaster on the inner masonry leaf commonly forms the building's airtight layer.
The window frame must therefore be connected continuously to this inner airtight layer. Sealing only the external side of the window does not necessarily provide airtightness to the interior.
Potential leakage paths through the cavity, unfinished blockwork or surrounding junctions may allow air to bypass an external seal.
Always connect the window to the intended continuous airtight layer of the building.
Before or After Window Installation?
In Ireland and the UK, window sealing is frequently completed after the window has been installed, with the tape applied to the visible frame surface and the surrounding reveal.
In other installation systems, tapes may be attached to the frame before the window is fitted. These products can have specially arranged adhesive strips for concealed frame connections.
Fully self-adhesive window tapes simplify installation by eliminating the need for a separate adhesive application on suitable substrates.
Substrate Preparation
Fully self-adhesive window tapes need a suitable bonding surface: clean, dry, stable and sufficiently even.
Porous or difficult surfaces may require a compatible primer. Rough or irregular masonry may first need a levelling or smoothing coat (Glattstrich) to create a continuous, suitable bonding surface.
Primer may improve adhesion, but it cannot compensate for significant surface irregularities.
Where reliable full-surface bonding cannot be achieved, a conventional window sealing tape with a frame adhesive strip and a separate compatible sealant connection to the building structure may be more suitable.
For suitable internal connections, (f)air tightness OR can help accommodate irregularities that a thin self-adhesive layer cannot. External weather-exposed connections require sealing products specifically suitable for that application.
5. Inspection & Quality Control
The Better It Looks, the Better It Will Perform
Neatly installed membranes, properly pressed tapes and carefully sealed junctions are strong indicators of good workmanship. A tidy installation is not proof of airtightness, but visible defects should never be ignored.
Remember that airtightness concerns the entire building. Roof membranes and window seals alone are not enough if there are unsealed gaps at floor-to-wall connections, roof junctions or service penetrations.
Inspect Before Covering
Check the completed airtight layer before installing plasterboard or other finishes. A second person carrying out an independent visual inspection can help identify overlooked details.
Repair all damaged areas and confirm that every overlap, penetration and connection has been sealed.
Protect the Work from Other Trades
Electricians, plumbers, ventilation installers and other trades must know where the airtight layer is located.
Any new penetrations should be agreed in advance where possible. If the airtight layer is subsequently drilled, cut or damaged, the affected area must be reported and properly resealed before the construction is closed.
Preliminary Airtightness Test – Quality Control
We strongly recommend a preliminary airtightness test once the airtight layer and its connections are complete, but while critical areas remain accessible.
The main purpose of this test is not to achieve or certify a particular airtightness figure. It is to check how the installed airtight layer performs and identify leakage locations while repairs are still practical.
A blower-door test, supported by suitable leakage-detection methods, can reveal problems at junctions, penetrations and other critical details.
The final airtightness test verifies the completed building under the applicable testing procedure. However, once walls, ceilings and finishes are closed, correcting concealed leakage paths can be difficult and expensive.
Preliminary Test: Find and fix problems.
Final Test: Verify the completed building.
Good airtightness is achieved during construction — not by relying on the final test to reveal what should have been corrected earlier.